New Zealand

Jervois Quay closure triggers Wellington commuter blockage


Traffic was at a standstill on several motorway exits on Friday morning, including the one onto Murphy Street, due to the closure of Jervois Quay

KEVIN STENT

Traffic was at a grinding halt on numerous freeway exits on Friday early morning, consisting of the one onto Murphy Street, due to the closure of Jervois Quay

Traffic in Wellington is when again developing due to a significant commuter path being closed in the capital.

Jervois Quay closed on Thursday night at 7pm to repair a damaged stormwater pipeline, and the roadway will not re-open till 6am on Tuesday.

As traffic began to construct with the night heavy traffic, Wellington City Council representative Richard MacLean stated individuals need to postpone travel by an hour if possible.

He advised if individuals required to cross the city over the weekend, they include an additional half hour travel time to their journey.

LEARN MORE:
* Wellingtonians prompted to reconsider strategies ahead of significant works
* Wellington sinkhole repair work ended up overnight, one lane still closed, hold-ups anticipated
* Commuters alerted of possible hold-ups once again due to sinkhole repair work

This early morning, traffic into Wellington main was supported as far as Ngauranga Gorge as commuter traffic was diverted by the closure of Jervois Quay today.

The blockage produced late arrivals to work for some, with roadways into the main city staying hectic as late as 11 am.

The Aotea Quay off-ramp stayed open however Murphy and Hawkestone St off-ramps were greatly crowded by the bigger volumes of traffic utilizing the alternative paths to Thorndon and Pipitea.

Jervois Quay was closed at 7pm on Thursday, for WellingtonWater to utilize the vacation to fix a damaged stormwater pipeline

Commuters on Friday morning in Wellington are warned to avoid Jervois Quay which is closed for pipe repairs.

KEVIN STENT

Commuters on Friday early morning in Wellington are alerted to prevent Jervois Quay which is closed for pipeline repair work.

Do you understand more? Email newstips@stuff.co.nz

The work was anticipated to be finished by 6am, June 8.

MacLean stated professionals would operate in 3 shifts all the time to finish what would generally be 6 weeks worth of work done over the Queens Birthday vacation weekend.

MacLean stated professionals were “throwing everything at it” to finish the work by Tuesday early morning.

He stated the works had actually included about 15 minutes to the journey from the freeway to the airport.

“There’s definitely congestion, but it’s not grinding the city to a halt,” MacLean stated.

As of 9am, a Waka Kotahi NZ Transport Agency spokesperson stated the blockage was mainly included with Wellington city centre.

Road users were encouraged to anticipate considerable hold-ups about Jervois Quay and prevent the location if possible.

Contractors begin replacing a strom water pipe beneath Jervois Quay on Thursday.

KEVIN STENT

Contractors start changing a strom pipes underneath Jervois Quay on Thursday.

Wellington Water advised individuals utilize alternative methods of transportation when taking a trip to locations in or about the location.

Metlink alerted of hold-ups to main Wellington bus services due to the anticipated blockage in the location.

All six lanes of Jervois Quay will be closed over Queens Birthday weekend as Wellington Water repair a broken storm water pipe.

Supplied

All 6 lanes of Jervois Quay will be closed over Queens Birthday weekend as Wellington Water repair work a damaged storm pipes.